Key Personnel:
Chuck Schlumpberger
Project Engineer

Project Duration:
Sept 2000 - Dec 2005

Reference Contact:
Tracie Mueller
Design Engineer
916-858-2721

 

 

Sewer Replacement, Phase I, II & III
McCloud Community Service District - McCloud, CA

This has been an ongoing project that was completed in three phases, and has been a cooperative effort between Kennedy/Jenks Consultants, one of the largest design firms on the West Coast, SCE, offering inspection services as well as construction management, and District Personnel. The project provided vital infrastructure improvements that consisted of replacement and installation of new sewer lines, installation of laterals and manholes, and rehabilitation of existing road surfaces along the project alignments throughout the city of McCloud.